Back to Case Studies
Multi-FamilyCalifornia8 Disciplines814 Issues

814 Issues Found in Multi-Building Residential Development

Fire protection conflicts, structural coordination gaps, accessibility violations, and MEP issues—all surfaced before permit submission.

814
Total Issues
47
Critical
298
High Severity
8
Disciplines

The Project

A multi-building residential development in California comprising multiple structures with shared parking, amenities, and site infrastructure. InspectMind performed a comprehensive QA/QC review across all disciplines, identifying critical coordination gaps between fire protection, structural, architectural, MEP, and civil systems that would have caused permit delays and costly field modifications.

2018 International Fire Code2022 CA Building CodeNFPA 13/72/20Structural loadsICC/ANSI A117.1

Issues by Discipline

Fire Protection

187 issues • Sprinkler coverage, alarms, FDC access

Structural & Seismic

142 issues • Seismic joints, hold-downs, connections

Architectural

156 issues • Egress, door hardware, headroom

MEP Systems

198 issues • HVAC, plumbing, electrical coordination

Accessibility

89 issues • ADA clearances, routes, Type A/B units

Site & Civil

42 issues • Grading, drainage, fire lane access

Sample Findings

CriticalFire ProtectionAttic Sprinkler Coverage Conflict

Fire sprinkler main routing through attic conflicts with 24\" o.c. prefab wood trusses. No deflector clearance or truss penetration details provided—sprinkler spray pattern potentially obstructed.

CriticalFire ProtectionFire Alarm NAC Voltage Drop

Notification Appliance Circuit extends 340 feet from FACP—at this distance, typical #14 AWG would exceed 10% voltage drop, causing horn/strobes to underperform during emergencies.

CriticalStructuralSeismic Joint Gap Discrepancy

Architectural shows 4\" seismic joint between buildings while structural shows 6\" at same location. This 2\" discrepancy affects joint covers, waterproofing, and building separation during earthquakes.

CriticalElectricalGenerator Undersized for Fire Pump

200 kW generator with 185 kW emergency load schedule doesn't include 50 HP fire pump (~40 kW). Combined load exceeds generator capacity—fire pump won't operate during power outage.

CriticalAccessibilityAccessible Unit Bathroom Door Swing

32\" door swinging into 5'x8' bathroom reduces clear floor space below 60\" turning diameter requirement—unit fails Fair Housing accessibility requirements.

HighStructuralHold-Down vs MEP Routing Conflict

Simpson HDU14 hold-down location conflicts with 4\" drain line—only 3\" clearance where anchor bolts and drain penetration both need space in foundation.

HighArchitecturalExit Corridor Width Reduced

Semi-recessed fire extinguisher cabinet projects 4\" into 44\" corridor, reducing clear width to 40\"—below CBC minimum for occupant load served.

HighPlumbingDrain Pitch Exceeds Floor Depth

4\" drain running 45 feet requires 5-5/8\" drop at minimum pitch, but only 4\" depth available in floor slab—pipe cannot achieve required slope.

Issue Categories

Fire Protection

Sprinkler coverage, alarm circuits, FDC access, stair pressurization, firestopping

Structural & Seismic

Seismic joints, hold-downs, shear walls, moment frames, pile capacity

Architectural

Egress paths, door hardware, stair dimensions, headroom, finishes

Mechanical (HVAC)

Equipment support, duct sizing, makeup air, condensate routing

Plumbing

Combustion air, drain pitch, roof drains, gas piping

Electrical

Generator sizing, fault current, conductor sizing, GFCI protection

Accessibility

Parking, elevators, routes, Type A/B units, grab bars

Site & Civil

Accessible routes, storm drainage, fire lanes, retaining walls

Value Delivered

814 issues identified before permit submission
47 critical life safety issues flagged
Fire protection/structural conflicts resolved
Accessibility compliance verified across all units
MEP routing conflicts identified before construction
Emergency power system sizing corrected

"The fire alarm voltage drop issue and generator undersizing would have caused major problems during commissioning. Catching these coordination gaps before permit saved us months of redesign and hundreds of thousands in change orders."

— Development Team

Want This Level of Review on Your Project?

Fast turnaround. Prioritized issue list with code references across all disciplines.

5+ issues guaranteed or full refund — no questions asked

From $100, cheaper than one RFI. No per-user fees. Share with your entire team. Invoice available for enterprise.

See sample report (282 issues found)

Not sure yet? Upload a completed project you already know — see what we catch. Most teams validate, then roll out across every job.

5+ issues or full refund
Find issues in minutes
No call required

Upload all project PDFs: drawings, specs, codes, checklists, shop drawings, submittals, contracts, zoning codes, city comments. AI checks everything against everything.

187,000+ issues caught across 500+ engineering and construction firms

One issue found pays for the whole check