Utah Commercial / Mixed-Use (Ogden): 453 Issues Found
An anonymized plan review in Ogden, Utah uncovered coordination and code issues across disciplines—before permit.
Key findings
Issue #555
Architectural • 2018 International Building Code
Issue #555
Issue #558
Architectural • 2018 International Building Code
Issue #558
Issue #522
Architectural • 2018 International Building Code
Issue #522
Issue #506
Architectural • 2018 International Building Code
Issue #506
Issue #398
Architectural
Issue #398
Issue #414
Architectural
Issue #414
Issue #357
Architectural
Issue #357
Issue #133
Architectural
Issue #133
Issue #32
Architectural
Issue #32
Issue #31
Architectural
Issue #31
Issue categories
More example findings
Issue #555Architectural • 2018 International Building CodeCritical
Summary: Issue #555
Why it matters: This coordination issue could lead to field conflicts and change orders in Commercial projects.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #555
Issue #558Architectural • 2018 International Building CodeCritical
Summary: Issue #558
Why it matters: This coordination issue could lead to field conflicts and change orders in Commercial projects.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #558
Issue #522Architectural • 2018 International Building CodeCritical
Summary: Issue #522
Why it matters: Failure to address this issue may result in construction delays and costly rework during Commercial construction.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #522
Issue #506Architectural • 2018 International Building CodeCritical
Summary: Issue #506
Why it matters: This issue could cause code violations and may prevent plan approval for Commercial projects.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #506
Issue #398ArchitecturalCritical
Summary: Issue #398
Why it matters: This issue could cause code violations and may prevent plan approval for Commercial projects.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #398
Issue #414ArchitecturalCritical
Summary: Issue #414
Why it matters: Addressing this issue before construction prevents costly rework and ensures code compliance for Commercial projects.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #414
Issue #357ArchitecturalCritical
Summary: Issue #357
Why it matters: Failure to address this issue may result in construction delays and costly rework during Commercial construction.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #357
Issue #133ArchitecturalCritical
Summary: Issue #133
Why it matters: This issue could cause code violations and may prevent plan approval for Commercial projects.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #133
Issue #32ArchitecturalCritical
Summary: Issue #32
Why it matters: This coordination issue could lead to field conflicts and change orders in Commercial projects.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #32
Issue #31ArchitecturalCritical
Summary: Issue #31
Why it matters: Addressing this issue before construction prevents costly rework and ensures code compliance for Commercial projects.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #31
Issue #237CivilCritical
Summary: Issue #237
Why it matters: Failure to address this issue may result in construction delays and costly rework during Commercial construction.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #237
Issue #38ArchitecturalCritical
Summary: Issue #38
Why it matters: This coordination issue could lead to field conflicts and change orders in Commercial projects.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #38
Issue #182MechanicalCritical
Summary: Issue #182
Why it matters: Addressing this issue before construction prevents costly rework and ensures code compliance for Commercial projects.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #182
Issue #183MechanicalCritical
Summary: Issue #183
Why it matters: Failure to address this issue may result in construction delays and costly rework during Commercial construction.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #183
Issue #167StructuralCritical
Summary: Issue #167
Why it matters: Failure to address this issue may result in construction delays and costly rework during Commercial construction.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #167
This is an anonymized example. Findings shown are excerpts for illustration. Actual project details have been modified to protect client confidentiality.