ArchitecturalStructuralCivilMechanical

Utah Commercial / Mixed-Use (Ogden): 453 Issues Found

An anonymized plan review in Ogden, Utah uncovered coordination and code issues across disciplines—before permit.

453
Issues found
5
Disciplines
5
Codes referenced

Key findings

Issue #555

Architectural • 2018 International Building Code

Critical

Issue #555

Issue #558

Architectural • 2018 International Building Code

Critical

Issue #558

Issue #522

Architectural • 2018 International Building Code

Critical

Issue #522

Issue #506

Architectural • 2018 International Building Code

Critical

Issue #506

Issue #398

Architectural

Critical

Issue #398

Issue #414

Architectural

Critical

Issue #414

Issue #357

Architectural

Critical

Issue #357

Issue #133

Architectural

Critical

Issue #133

Issue #32

Architectural

Critical

Issue #32

Issue #31

Architectural

Critical

Issue #31

Issue categories

Architectural
Egress, accessibility, room layouts, building code compliance, and finish specifications
Structural
Structural connections, load paths, foundation design, and structural code compliance
Civil
Civil code compliance and coordination issues
Mechanical
HVAC systems, ventilation, exhaust, refrigerant piping, and mechanical code compliance
Plumbing
Plumbing fixtures, drainage, venting, water supply, and plumbing code compliance

More example findings

Issue #555
Architectural • 2018 International Building Code
Critical

Summary: Issue #555

Why it matters: This coordination issue could lead to field conflicts and change orders in Commercial projects.

Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.

RFI draft: Please clarify: Issue #555

Issue #558
Architectural • 2018 International Building Code
Critical

Summary: Issue #558

Why it matters: This coordination issue could lead to field conflicts and change orders in Commercial projects.

Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.

RFI draft: Please clarify: Issue #558

Issue #522
Architectural • 2018 International Building Code
Critical

Summary: Issue #522

Why it matters: Failure to address this issue may result in construction delays and costly rework during Commercial construction.

Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.

RFI draft: Please clarify: Issue #522

Issue #506
Architectural • 2018 International Building Code
Critical

Summary: Issue #506

Why it matters: This issue could cause code violations and may prevent plan approval for Commercial projects.

Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.

RFI draft: Please clarify: Issue #506

Issue #398
Architectural
Critical

Summary: Issue #398

Why it matters: This issue could cause code violations and may prevent plan approval for Commercial projects.

Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.

RFI draft: Please clarify: Issue #398

Issue #414
Architectural
Critical

Summary: Issue #414

Why it matters: Addressing this issue before construction prevents costly rework and ensures code compliance for Commercial projects.

Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.

RFI draft: Please clarify: Issue #414

Issue #357
Architectural
Critical

Summary: Issue #357

Why it matters: Failure to address this issue may result in construction delays and costly rework during Commercial construction.

Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.

RFI draft: Please clarify: Issue #357

Issue #133
Architectural
Critical

Summary: Issue #133

Why it matters: This issue could cause code violations and may prevent plan approval for Commercial projects.

Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.

RFI draft: Please clarify: Issue #133

Issue #32
Architectural
Critical

Summary: Issue #32

Why it matters: This coordination issue could lead to field conflicts and change orders in Commercial projects.

Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.

RFI draft: Please clarify: Issue #32

Issue #31
Architectural
Critical

Summary: Issue #31

Why it matters: Addressing this issue before construction prevents costly rework and ensures code compliance for Commercial projects.

Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.

RFI draft: Please clarify: Issue #31

Issue #237
Civil
Critical

Summary: Issue #237

Why it matters: Failure to address this issue may result in construction delays and costly rework during Commercial construction.

Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.

RFI draft: Please clarify: Issue #237

Issue #38
Architectural
Critical

Summary: Issue #38

Why it matters: This coordination issue could lead to field conflicts and change orders in Commercial projects.

Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.

RFI draft: Please clarify: Issue #38

Issue #182
Mechanical
Critical

Summary: Issue #182

Why it matters: Addressing this issue before construction prevents costly rework and ensures code compliance for Commercial projects.

Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.

RFI draft: Please clarify: Issue #182

Issue #183
Mechanical
Critical

Summary: Issue #183

Why it matters: Failure to address this issue may result in construction delays and costly rework during Commercial construction.

Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.

RFI draft: Please clarify: Issue #183

Issue #167
Structural
Critical

Summary: Issue #167

Why it matters: Failure to address this issue may result in construction delays and costly rework during Commercial construction.

Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.

RFI draft: Please clarify: Issue #167

This is an anonymized example. Findings shown are excerpts for illustration. Actual project details have been modified to protect client confidentiality.

Want this on your next set?

Fast turnaround. Anonymized outputs available for sharing internally.