Infrastructure Remote Terminal: 416 Issues Found
An anonymized infrastructure remote terminal plan review uncovered issues in civil, structural, and MEP coordination—before construction.
Key findings
Issue #438
Structural
Issue #438
Issue #379
Fire Protection • NFPA 70
Issue #379
Issue #297
Architectural
Issue #297
Issue #371
Electrical
Issue #371
Issue #354
Mechanical
Issue #354
Issue #223
Plumbing
Issue #223
Issue #237
Plumbing
Issue #237
Issue #230
Technology
Issue #230
Issue #166
Architectural
Issue #166
Issue #169
Architectural
Issue #169
Issue categories
More example findings
Issue #438StructuralCritical
Summary: Issue #438
Why it matters: This issue could cause code violations and may prevent plan approval for Infrastructure projects.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #438
Issue #379Fire Protection • NFPA 70Critical
Summary: Issue #379
Why it matters: Failure to address this issue may result in construction delays and costly rework during Infrastructure construction.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #379
Issue #297ArchitecturalCritical
Summary: Issue #297
Why it matters: This coordination issue could lead to field conflicts and change orders in Infrastructure projects.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #297
Issue #371ElectricalCritical
Summary: Issue #371
Why it matters: This coordination issue could lead to field conflicts and change orders in Infrastructure projects.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #371
Issue #354MechanicalCritical
Summary: Issue #354
Why it matters: This issue could cause code violations and may prevent plan approval for Infrastructure projects.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #354
Issue #223PlumbingCritical
Summary: Issue #223
Why it matters: This issue could cause code violations and may prevent plan approval for Infrastructure projects.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #223
Issue #237PlumbingCritical
Summary: Issue #237
Why it matters: Addressing this issue before construction prevents costly rework and ensures code compliance for Infrastructure projects.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #237
Issue #230TechnologyCritical
Summary: Issue #230
Why it matters: This issue could cause code violations and may prevent plan approval for Infrastructure projects.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #230
Issue #166ArchitecturalCritical
Summary: Issue #166
Why it matters: This coordination issue could lead to field conflicts and change orders in Infrastructure projects.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #166
Issue #169ArchitecturalCritical
Summary: Issue #169
Why it matters: Failure to address this issue may result in construction delays and costly rework during Infrastructure construction.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #169
Issue #156ArchitecturalCritical
Summary: Issue #156
Why it matters: This issue could cause code violations and may prevent plan approval for Infrastructure projects.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #156
Issue #111StructuralCritical
Summary: Issue #111
Why it matters: Addressing this issue before construction prevents costly rework and ensures code compliance for Infrastructure projects.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #111
Issue #160ArchitecturalCritical
Summary: Issue #160
Why it matters: Addressing this issue before construction prevents costly rework and ensures code compliance for Infrastructure projects.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #160
Issue #121StructuralCritical
Summary: Issue #121
Why it matters: This coordination issue could lead to field conflicts and change orders in Infrastructure projects.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #121
Issue #154StructuralCritical
Summary: Issue #154
Why it matters: Failure to address this issue may result in construction delays and costly rework during Infrastructure construction.
Suggested next step: Review drawings and specifications to resolve this conflict before construction begins.
RFI draft: Please clarify: Issue #154
This is an anonymized example. Findings shown are excerpts for illustration. Actual project details have been modified to protect client confidentiality.