Wastewater Support Building: 51 Issues Flagged

Review pre-engineered building loads, stair geometry, and the governing code references before delegated design.

51
Potential findings
2
Disciplines
3
Published examples
Start with $100 creditSee the findings

Enterprise & volume pricing

Anonymized review · Published 2026-09-16

What this review documents

Review pre-engineered building loads, stair geometry, and the governing code references before delegated design.

The documented result is a set of review findings. This case study does not establish that corrections were completed or that savings were realized. The examples below were marked useful in the source review record; they have been paraphrased to remove identifying details.

Open the sample report →See pricing →Read our measurement definitions →

Key findings

Suspended-load allowances differ

Structural

High

Drawings list seven psf of collateral load, while the specification separately lists twelve psf for suspended MEP and five psf for ceilings.

Next step: Reconcile the required load cases and allocations with the building-system supplier.

Stair tread dimension is labeled maximum

Structural / Architectural

High

A stair detail labels the tread run as eleven inches maximum. The review flagged whether a minimum dimension was intended.

Next step: Have the architect confirm the applicable geometry and correct the minimum/maximum notation.

Governing code edition differs between notes

Structural

Medium

Different structural notes cite different editions of the same state building code.

Next step: Confirm the governing edition and amendments and make the document references consistent.

Issue categories

Structural
Structural findings in the selected review excerpts.
Structural / Architectural
Structural / Architectural findings in the selected review excerpts.

Review details and suggested questions

Suspended-load allowances differ
Structural
High

Summary: Drawings list seven psf of collateral load, while the specification separately lists twelve psf for suspended MEP and five psf for ceilings.

Why it matters: This discrepancy leaves the design team or contractor with conflicting instructions. Resolve the governing requirement before relying on the affected documents.

Suggested next step: Reconcile the required load cases and allocations with the building-system supplier.

RFI draft: Reconcile the required load cases and allocations with the building-system supplier.

Stair tread dimension is labeled maximum
Structural / Architectural
High

Summary: A stair detail labels the tread run as eleven inches maximum. The review flagged whether a minimum dimension was intended.

Why it matters: This discrepancy leaves the design team or contractor with conflicting instructions. Resolve the governing requirement before relying on the affected documents.

Suggested next step: Have the architect confirm the applicable geometry and correct the minimum/maximum notation.

RFI draft: Have the architect confirm the applicable geometry and correct the minimum/maximum notation.

Governing code edition differs between notes
Structural
Medium

Summary: Different structural notes cite different editions of the same state building code.

Why it matters: This discrepancy leaves the design team or contractor with conflicting instructions. Resolve the governing requirement before relying on the affected documents.

Suggested next step: Confirm the governing edition and amendments and make the document references consistent.

RFI draft: Confirm the governing edition and amendments and make the document references consistent.

Anonymized, paraphrased excerpts from a completed project review. These three examples were marked “good catch” in the source review record; that label is feedback, not independent validation. The project total excludes duplicate-group members, dismissed findings, wrong finds, and insufficient-reference findings. Only selected excerpts are published. Customer identity, project address, source identifiers, and private drawings are omitted. Corrections, permit outcomes, and financial savings have not been independently verified. A qualified professional should assess each finding against the complete project documents.

Related case studies

Similar AI plan review results by project type and discipline. Browse all case studies

First $100 covered

Want this on your next set?

Start with the first $100 covered. See cited issues in hours, no call required.

  • Evidence-linked findings
  • 5+ issues or full refund
  • Results in hours

5+ issues or full refund · No demo required

View all case studies|See pricing