Ontario Commercial Plan Review: 305 Issues Found
An anonymized Ontario commercial plan review uncovered coordination and code issues across disciplines, before permit.
Free check on up to 10 drawing pages. Enterprise and volume pricing
- 1Critical · ArchitecturalConflicting Fume Hood Quantities in Chemistry Lab 450
- 2Critical · ElectricalFire Alarm System Type Discrepancy (Single-Stage vs. Two-Stage / Horns vs. Speakers)
- 3Critical · ElectricalMiele Washer Phase and Circuit Poles Mismatch
Fig. 1 · Top findings, pinned on the set
- Potential findings
- 305
- Disciplines
- 5
- Codes referenced
- 2
- Critical or high examples shown
- 15
Checkers used on this project
Run the same check on your set →About this review
InspectMind ran an AI plan review on this project set and returned 305 potential findings across Architectural, Electrical, General, Mechanical, Plumbing. The selected examples below show the document conflict, why it matters, and a suggested next step.
- Disciplines
- Architectural, Electrical, General, Mechanical, Plumbing
- Potential findings
- 305
- Examples shown
- 15
Key findings
- 1Critical
Conflicting Fume Hood Quantities in Chemistry Lab 450
Architectural
Architectural plan A-706 depicts a single large fume hood (FH-1) in Chemistry Lab 450. However, the Mechanical P&ID (M-013.11) diagrams three fume hoods connected to the exhaust system for this room, which aligns with the Mechanical Controls schedule (M-801) that explicitly lists three fume hoods (Fume Hood 1, 2, and 3) for the same space.
- 2Critical
Fire Alarm System Type Discrepancy (Single-Stage vs. Two-Stage / Horns vs. Speakers)
Electrical
Drawing E-721 explicitly details the system in its sequence of operations as a '(SINGLE STAGE F/A SYSTEM)' and the schedule symbols only list 'FIRE ALARM HORN' and 'FIRE ALARM HORN/STROBE'. However, Drawing E-720 directly contradicts this by requiring 'ONE SPEAKER ZONE PER LEVEL AND ONE SPEAKER ZONE FOR EACH STAIRWELL' (General Note 4) and...
- 3Critical
Miele Washer Phase and Circuit Poles Mismatch
Electrical
Keynote 3 specifies a '3-PHASE 30A' connection for the Miele Washers, which requires a 3-pole circuit breaker and 3 circuit slots (e.g., 4N1-41,43,45). However, the plan tags the connections as 2-pole circuits (4N1-43,45 and 4N1-40,42), and Panel Schedule RP-CE-4N1 confirms these circuits have only 2 poles.
- 4Critical
Physical and Code Coordination Conflicts Between Plumbing Vents (VTR) and HVAC Equipment
Plumbing
The Plumbing Plan (M-250) designates multiple Vent Thru Roof (VTR) and Acid Relief Vents (VTR (AR)) at locations that physically clash with HVAC equipment shown on the HVAC Plan (M-351). Specifically, M-250 shows VTRs directly adjacent to AHU-5 and at grid intersections B-7 and C-7. However, M-351 locates Exhaust Fans (EF-41A, EF-46A, EF-38,...
- 5Critical
Motorized Latch Retraction (MLR) incorrectly specifies 120V direct power
Electrical
The electrical legend indicates to 'PROVIDE 120 V.' for the Motorized Latch Retraction (MLR). However, the Finish Hardware specification explicitly requires electrified hardware to operate via power supplies that provide a 'low voltage DC output' (12/24VDC). Providing 120V is only applicable to the hardware power supply unit itself, not...
- 6Critical
Improper Sealant Specified Around Floor Sleeves in Fire Separations
Electrical
Detail 5 requires packing the inside of the steel sleeve with 'FIRE STOP MATERIAL', which indicates the floor slab is treated as a fire separation. However, it specifies 'SILICON CAULKING AROUND STEEL SLEEVE' for the exterior annular space between the concrete slab and the steel sleeve. Section 07 84 10 requires listed firestop and smoke seal...
- 7Critical
Firestop F-Rating Conflict for Penetrations in Fire-Protected Structures
General
The drawing note in the FIRE SEPARATIONS LEGEND states that walls with a 'FIRE PROTECTED STRUCTURE RATING' shall be constructed as 0 HR fire separations with respect to penetrations. This directly contradicts the specification, which mandates that the F-Rating for firestopping must not be less than the fire-resistance rating of the construction...
- 8Critical
Fire-Rated Exit Stairwell Doors Missing Closer Designation
Architectural
The Code Plan assigns a '45 | - | CR' tag to the doors leading into the exit stairwells. According to the 'FIRE PROTECTED CLOSURES LEGEND', the second position in this tag designates the 'CLOSURE OPERATION CONTROL DEVICE', and a '-' explicitly indicates that no closure device is specified. However, Specification Section 08 11 13 requires all...
- 9Critical
Conflicting nomenclature for 'PT-#' paint designation
Architectural
Specification Section 09 91 23 designates 'PT#' for architectural interior finishes, specifically defining 'PT-1' as a High-Performance Epoxy and 'PT-2' as a Standard Performance Latex. However, the Code Plan Legend on drawing A-021 explicitly defines the 'PT-#' tag as '1HR INTUMESCENT PAINT'.
- 10Critical
Casework Schedule Specifies 'Steel' Instead of 'Stainless Steel'
Architectural
The casework schedule explicitly lists multiple base cabinetry items (e.g., CW-002-3-L-A, CW-009-3-x-A) as standard 'STEEL BASE CABINETS' or 'STEEL_BASE_CABINETS'. However, Specification Section 12 35 71 mandates that all steel furniture under this section must be constructed of stainless steel.
Issue categories
- Cat. 01Architectural
- Egress, accessibility, room layouts, building code compliance, and finish specifications
- Cat. 02Electrical
- Electrical systems, panelboards, circuits, and electrical code compliance
- Cat. 03Mechanical
- HVAC systems, ventilation, exhaust, and mechanical code compliance
- Cat. 04Plumbing
- Plumbing fixtures, drainage, venting, water supply, and plumbing code compliance
- Cat. 05General
- Drawing index, coordination, and general plan review findings
Review details and suggested questions
01Conflicting Fume Hood Quantities in Chemistry Lab 450Architectural
Critical
Architectural
Summary: Architectural plan A-706 depicts a single large fume hood (FH-1) in Chemistry Lab 450. However, the Mechanical P&ID (M-013.11) diagrams three fume hoods connected to the exhaust system for this room, which aligns with the Mechanical Controls schedule (M-801) that explicitly lists three fume hoods (Fume Hood 1, 2, and 3) for the same space.
Why it matters:
Suggested next step:
RFI draft:
02Fire Alarm System Type Discrepancy (Single-Stage vs. Two-Stage / Horns vs. Speakers)Electrical
Critical
Electrical
Summary: Drawing E-721 explicitly details the system in its sequence of operations as a '(SINGLE STAGE F/A SYSTEM)' and the schedule symbols only list 'FIRE ALARM HORN' and 'FIRE ALARM HORN/STROBE'. However, Drawing E-720 directly contradicts this by requiring 'ONE SPEAKER ZONE PER LEVEL AND ONE SPEAKER ZONE FOR EACH STAIRWELL' (General Note 4) and...
Why it matters:
Suggested next step:
RFI draft:
03Miele Washer Phase and Circuit Poles MismatchElectrical
Critical
Electrical
Summary: Keynote 3 specifies a '3-PHASE 30A' connection for the Miele Washers, which requires a 3-pole circuit breaker and 3 circuit slots (e.g., 4N1-41,43,45). However, the plan tags the connections as 2-pole circuits (4N1-43,45 and 4N1-40,42), and Panel Schedule RP-CE-4N1 confirms these circuits have only 2 poles.
Why it matters:
Suggested next step:
RFI draft:
04Physical and Code Coordination Conflicts Between Plumbing Vents (VTR) and HVAC EquipmentPlumbing
Critical
Plumbing
Summary: The Plumbing Plan (M-250) designates multiple Vent Thru Roof (VTR) and Acid Relief Vents (VTR (AR)) at locations that physically clash with HVAC equipment shown on the HVAC Plan (M-351). Specifically, M-250 shows VTRs directly adjacent to AHU-5 and at grid intersections B-7 and C-7. However, M-351 locates Exhaust Fans (EF-41A, EF-46A, EF-38,...
Why it matters:
Suggested next step:
RFI draft:
05Motorized Latch Retraction (MLR) incorrectly specifies 120V direct powerElectrical
Critical
Electrical
Summary: The electrical legend indicates to 'PROVIDE 120 V.' for the Motorized Latch Retraction (MLR). However, the Finish Hardware specification explicitly requires electrified hardware to operate via power supplies that provide a 'low voltage DC output' (12/24VDC). Providing 120V is only applicable to the hardware power supply unit itself, not...
Why it matters:
Suggested next step:
RFI draft:
06Improper Sealant Specified Around Floor Sleeves in Fire SeparationsElectrical
Critical
Electrical
Summary: Detail 5 requires packing the inside of the steel sleeve with 'FIRE STOP MATERIAL', which indicates the floor slab is treated as a fire separation. However, it specifies 'SILICON CAULKING AROUND STEEL SLEEVE' for the exterior annular space between the concrete slab and the steel sleeve. Section 07 84 10 requires listed firestop and smoke seal...
Why it matters:
Suggested next step:
RFI draft:
07Firestop F-Rating Conflict for Penetrations in Fire-Protected StructuresGeneral
Critical
General
Summary: The drawing note in the FIRE SEPARATIONS LEGEND states that walls with a 'FIRE PROTECTED STRUCTURE RATING' shall be constructed as 0 HR fire separations with respect to penetrations. This directly contradicts the specification, which mandates that the F-Rating for firestopping must not be less than the fire-resistance rating of the construction...
Why it matters:
Suggested next step:
RFI draft:
08Fire-Rated Exit Stairwell Doors Missing Closer DesignationArchitectural
Critical
Architectural
Summary: The Code Plan assigns a '45 | - | CR' tag to the doors leading into the exit stairwells. According to the 'FIRE PROTECTED CLOSURES LEGEND', the second position in this tag designates the 'CLOSURE OPERATION CONTROL DEVICE', and a '-' explicitly indicates that no closure device is specified. However, Specification Section 08 11 13 requires all...
Why it matters:
Suggested next step:
RFI draft:
09Conflicting nomenclature for 'PT-#' paint designationArchitectural
Critical
Architectural
Summary: Specification Section 09 91 23 designates 'PT#' for architectural interior finishes, specifically defining 'PT-1' as a High-Performance Epoxy and 'PT-2' as a Standard Performance Latex. However, the Code Plan Legend on drawing A-021 explicitly defines the 'PT-#' tag as '1HR INTUMESCENT PAINT'.
Why it matters:
Suggested next step:
RFI draft:
10Casework Schedule Specifies 'Steel' Instead of 'Stainless Steel'Architectural
Critical
Architectural
Summary: The casework schedule explicitly lists multiple base cabinetry items (e.g., CW-002-3-L-A, CW-009-3-x-A) as standard 'STEEL BASE CABINETS' or 'STEEL_BASE_CABINETS'. However, Specification Section 12 35 71 mandates that all steel furniture under this section must be constructed of stainless steel.
Why it matters:
Suggested next step:
RFI draft:
11Dimensional Conflict in M. WASH 416 Top Wall LayoutArchitectural
Critical
Architectural
Summary: The overall interior width of the top wall in M. WASH 416 is dimensioned as 4736 mm. However, the continuous run of individual dimensions along this wall (urinal area 771 mm + urinal area 942 mm + standard WC stall 925 mm + barrier-free WC stall 2165 mm, which are dimensioned to the centerlines of the partitions) sums to 4803 mm. This sum...
Why it matters:
Suggested next step:
RFI draft:
12Hardware Groups omitted from Door Schedule and SpecificationArchitectural
Critical
Architectural
Summary: The Door Schedule includes a column for 'HARDWARE GROUP', but it is completely blank for all doors. Furthermore, Specification Section 08 71 00 (Section 3.6 Hardware Groups) contains no hardware sets, leaving the project without any defined hardware configurations.
Why it matters:
Suggested next step:
RFI draft:
13Reheat Coils (RHC) Power Design Conflicts with Hydronic SpecificationElectrical
Critical
Electrical
Summary: The electrical drawings specify dedicated line-voltage and 3-phase power circuits (e.g., 3-pole breakers 4NB-35,37,39 and 4NB-13,15,17) connected directly to Reheat Coils (tagged RHC), which designates a design for high-amperage Electric Reheat Coils. However, the mechanical specifications explicitly require 'hot water reheat coils' and outline...
Why it matters:
Suggested next step:
RFI draft:
14New Air Handling Units Excluded from Systems Scope via Keynote 1Electrical
Critical
Electrical
Summary: Drawing E-450 places Keynote 1 ('AREA NOT IN SCOPE') directly onto the footprints of the newly scheduled air handling units (AHU-16A, 16B, 16C, 16D). However, Specification 23 74 14 Section 3.1.1 mandates to 'Provide outdoor modular air handling units on roof'. Furthermore, Specification 23 74 14 Section 2.2.11.4 requires the Systems...
Why it matters:
Suggested next step:
RFI draft:
15Packaged AHUs incorrectly shown fed through external VFDs on main power circuitsElectrical
Critical
Electrical
Summary: The electrical single-line diagrams (Details 1 and 3 on E-702) show the main 125A and 150A branch power circuits for the Air Handling Units (e.g., AHU-1A, AHU-16B) feeding through external Variable Frequency Drives (VFDs). However, per mechanical specification 23 74 14, these modular AHUs are fully packaged units that require a standard main...
Why it matters:
Suggested next step:
RFI draft:
This is an anonymized example. Findings shown are excerpts for illustration. Actual project details have been modified to protect client confidentiality.
Related case studies
Similar AI plan review results by project type and discipline.
- CommercialOttawa Commercial Plan Review: 2731 Issues Found2,731issues · Architectural, Civil
- CommercialSouth Texas Commercial Plan Review: 1021 Issues Found1,021issues · Architectural, Civil
- CommercialCalifornia Commercial Plan Review: 920 Issues Found920issues · Architectural, Civil
- CommercialOntario Commercial Plan Review: 425 Issues Found425issues · Architectural, Civil
- MEP CommercialPlan Review: 329 Issues Found329issues · Architectural, Electrical
- MultifamilySenior Lofts Plan Review: 325 Issues Found325issues · Architectural, Civil