364 Issues Found in New Church Construction Documents
Undersized septic systems, Title 24 non-compliance, accessibility violations, egress deficiencies, and hundreds of cross-document contradictions, all caught before permit submission.
First $100 covered. Enterprise and volume pricing
- Issues found
- 364
- Critical
- 35
- High priority
- 160
- Disciplines
- 8
The project
35 critical issues including undersized septic tank (30% below code requirements), Title 24 mandatory measures failure, and egress capacity violations for 633-person occupancy, any one of which would have caused permit rejection.
A new ~11,000 SF religious facility with Assembly Group A-3 occupancy, designed for up to 633 occupants. The project included a sanctuary, social hall, classrooms, kitchen, and support spaces, with on-site septic and well systems. InspectMind reviewed architectural, structural, mechanical, electrical, plumbing, civil, and fire protection drawings against the full specification package.
- Project type
- Religious facility · Assembly (A-3) · Multi-discipline
Codes referenced: 2022 CBC · California Title 24 · CPC / UPC · ADA / CBC 11B · NEC / CEC
Critical findings
- Critical
Septic Tank 30-35% Undersized
2,000 gallon tank specified when calculations show 2,840-3,088 gallons required per CPC Appendix H. Would cause permit rejection and potential system failure.
- Critical
Title 24 Mandatory Measures Non-Compliance
Certificate of Compliance explicitly states "DOES NOT COMPLY" for mandatory measures, a direct contradiction to project specification requirements for code compliance.
- Critical
Gas Connection Shown with No Gas Service
Project Directory shows Gas utility as "N/A", yet plumbing details show gas inlet and piping for water heater. Fundamental conflict about utility availability.
- Critical
Egress Capacity Conflict (633 Occupants vs. 2 Exits)
Code compliance block states 2 exits for occupancy under 500, but specifications show 633 occupants requiring 3 exits. Life safety violation.
- Critical
Plan vs. Elevation Major Discrepancies
Men's restroom floor plan shows 4 toilet stalls and 3 lavatories, but elevations show different fixtures entirely, fundamental coordination failure between views.
- Critical
Site Data Contradictions Across Sheets
Different addresses (2700 vs 7200 Central Ave), APNs (034 vs 035), lot areas (5.07 vs 2.68 AC), and building areas (11,000 vs 10,795 SF) between cover sheet and site analysis.
- Critical
Circuit Overload on Panel A
Circuit 17 shows 2.46 kW load (20.5 amps at 120V) on a 20-amp breaker, NEC overcurrent protection violation.
- Critical
RTU Capacity Input Error (1000x)
Equipment schedule shows 23,800 and 47,000 under "kBtu/h" columns, implying millions of BTU/h for small commercial AC units. Values likely entered in Btu/h instead of kBtu/h.
Additional high-priority findings
- High
Accessibility Door Force Violation
Drawing permits 8.5 lbs exterior door force; specification requires maximum 5 lbs, 70% over limit.
- High
Lavatory Toe Clearance Contradiction
Drawing shows 6" maximum toe clearance; specification requires 17" minimum, values are inverted.
- High
Building Sewer Slope Below Code
Detail specifies 0.25-0.5% slope; UPC requires minimum ~2% for building sewers.
- High
Conditioned Floor Area Exceeds Building Area
Title 24 shows 11,100 SF conditioned; architectural shows 10,795 SF total building, mathematical impossibility.
- High
Accessible Parking Length Undersized
Van accessible stall shows 16'-0"; specification requires 18'-0" minimum, 2 feet short.
- High
HVAC Equipment Misclassified as Residential
Title 24 form classifies exhaust fans as serving "Dwelling Units" in an A-3 church occupancy, triggers incorrect ventilation standards.
- High
Aluminum Wiring Contradiction
Drawing notes allow aluminum conductors; specifications explicitly prohibit aluminum wiring.
- High
Structural Lumber Grade Conflict
Beam schedule specifies Douglas Fir #2 for 6x members; specification requires #1 grade for beams 6x and greater.
Issue categories
- Plumbing & Septic
- Undersized septic tank, slope violations, trap requirements, conflicting pipe sizes
- Mechanical & Title 24
- Non-compliance certificates, equipment misclassification, capacity errors
- Electrical
- Circuit overloads, panel schedule conflicts, code version contradictions
- Accessibility / ADA
- Door forces, toe clearances, grab bar dimensions, signage conflicts
- Fire Life Safety
- Egress capacity, exit requirements, panic hardware contradictions
- Structural
- Lumber grades, fire blocking spacing, mixed framing materials
- Architectural
- Plan vs. elevation conflicts, finish schedule contradictions, room numbering
- Civil & Site
- Property data conflicts, grading issues, erosion control contradictions
Issue severity breakdown
- Critical
- 35 · Permit blockers, code violations
- High
- 160 · Significant coordination issues
- Medium
- 160 · Specification conflicts
- Low
- 9 · Minor drafting issues
Value delivered
- 364 issues surfaced in automated review
- 35 permit-blocking critical issues identified
- Cross-sheet and spec-drawing reconciliation
- California code compliance verified (CBC, Title 24, CPC)
- Accessibility (CBC 11B / ADA) violations caught
- Life safety and egress deficiencies flagged
“I've been in this business for 50 years and this will change the way we do business. This will save me so much time and money. I'm liking what I am seeing. It has some fruitful beginnings. Good work!”
Why assembly occupancies require rigorous QA/QC
Religious facilities, event centers, and other Group A (Assembly) occupancies face heightened scrutiny from plan checkers and inspectors. With occupant loads often exceeding 500 people, issues with egress, fire protection, accessibility, and utility capacity become life-safety matters.
This project demonstrated how even experienced design teams can have coordination gaps across an 11,000 SF facility with multiple disciplines. From fundamental utility conflicts (gas piping shown with no gas service) to mathematical impossibilities (conditioned area exceeding building area), automated review catches what manual review often misses.
Related case studies
Similar AI plan review results by project type and discipline.
- CommercialUrban Commercial: 112 Issues Found112 issues · Structural, Unspecified
- CommercialMixed-Use / Commercial: 386 Issues Found386 issues · Structural, Architectural
- CivilPlan Review: 87 Issues Found87 issues · Architectural, Civil
- CivilPlan Review: 232 Issues Found232 issues · Architectural, Civil
- InfrastructureSolar Facility: 31 Issues Found31 issues · Structural, Electrical
- MEP CommercialPlan Review: 5199 Issues Found5,199 issues · Architectural, Civil