Multifamily Buildings, Central Massachusetts: 1,006 Issues Flagged

Check shaft ratings, foundation datums, and shear wall sheathing across a multi-building residential set.

Anonymized review · Published 2026-11-09

Free check on up to 10 drawing pages. Enterprise and volume pricing

1,006Potential findings
Flagged
  1. 1Critical · Architectural / Structural / Fire ProtectionElevator hoistway walls are rated 1 hour in a four-story building
  2. 2Critical · Architectural / StructuralFoundation elevations conflict with the building datum by about 12 feet
  3. 3Critical · Structural / ArchitecturalExterior shear walls rely on foam-composite sheathing with no shear basis

Fig. 1 · Top findings, pinned on the set

Potential findings
1,006
Disciplines
7
Published examples
3
Critical or high examples shown
3

Checkers used on this project

Run the same check on your set →
Sheet 01·Case file

About this review

InspectMind ran an AI plan review on this multifamily set and returned 1,006 potential findings across Architectural, Structural, Civil, Fire Protection, Mechanical, Plumbing, Electrical. The selected examples below show the document conflict, why it matters, and a suggested next step.

Project type
Multifamily
Disciplines
Architectural, Structural, Civil, Fire Protection, Mechanical, Plumbing, Electrical
Potential findings
1,006
Published examples
3
Published
2026-11-09
Evidence status
Selected from open findings in the source review record

What this review documents

Check shaft ratings, foundation datums, and shear wall sheathing across a multi-building residential set.

The documented result is a set of review findings. This case study does not establish that corrections were completed or that savings were realized. The examples below were marked useful in the source review record; they have been paraphrased to remove identifying details.

Key findings

  1. 1

    Elevator hoistway walls are rated 1 hour in a four-story building

    Architectural / Structural / Fire Protection · IBC 713.4

    Critical

    Elevator plans tag the hoistway walls with a 1-hour CMU partition type, while the building section shows four stories. Shaft enclosures connecting four or more stories need a 2-hour rating.

    Next step: Change the hoistway partition type to a 2-hour assembly and update the wall type schedule.

  2. 2

    Foundation elevations conflict with the building datum by about 12 feet

    Architectural / Structural

    Critical

    Wall-step elevations on the foundation plan for three of the buildings do not match the level elevations on the building elevations and sections, with offsets of roughly 12'-4".

    Next step: Reconcile the building datum and restate the foundation step elevations.

  3. 3

    Exterior shear walls rely on foam-composite sheathing with no shear basis

    Structural / Architectural

    Critical

    Exterior wall details show a foam-composite insulated sheathing panel applied directly to load-bearing wood framing, while the structural shear wall detail calls for wood structural panels with set thickness and edge nailing.

    Next step: Confirm the shear wall sheathing and detail how the insulated sheathing layers with the structural panel and nailing.

Issue categories

Cat. 01Architectural / Structural / Fire Protection
Architectural / Structural / Fire Protection findings in the selected review excerpts.
Cat. 02Architectural / Structural
Architectural / Structural findings in the selected review excerpts.
Cat. 03Structural / Architectural
Structural / Architectural findings in the selected review excerpts.

Review details and suggested questions

01
Elevator hoistway walls are rated 1 hour in a four-story building

Architectural / Structural / Fire Protection · IBC 713.4

Critical

Summary: Elevator plans tag the hoistway walls with a 1-hour CMU partition type, while the building section shows four stories. Shaft enclosures connecting four or more stories need a 2-hour rating.

Why it matters: An under-rated shaft is a permit comment at best and a field fix to built masonry at worst.

Suggested next step: Change the hoistway partition type to a 2-hour assembly and update the wall type schedule.

RFI draft: Change the hoistway partition type to a 2-hour assembly and update the wall type schedule.

02
Foundation elevations conflict with the building datum by about 12 feet

Architectural / Structural

Critical

Summary: Wall-step elevations on the foundation plan for three of the buildings do not match the level elevations on the building elevations and sections, with offsets of roughly 12'-4".

Why it matters: Footings formed to the wrong datum affect every grade, slab, and utility connection that follows.

Suggested next step: Reconcile the building datum and restate the foundation step elevations.

RFI draft: Reconcile the building datum and restate the foundation step elevations.

03
Exterior shear walls rely on foam-composite sheathing with no shear basis

Structural / Architectural

Critical

Summary: Exterior wall details show a foam-composite insulated sheathing panel applied directly to load-bearing wood framing, while the structural shear wall detail calls for wood structural panels with set thickness and edge nailing.

Why it matters: If the insulated panel replaces the structural panel, the walls lose their documented lateral capacity.

Suggested next step: Confirm the shear wall sheathing and detail how the insulated sheathing layers with the structural panel and nailing.

RFI draft: Confirm the shear wall sheathing and detail how the insulated sheathing layers with the structural panel and nailing.

Anonymized, paraphrased excerpts from a completed project review. These three examples were selected editorially from findings the source review record kept open (not dismissed or marked wrong); that selection is not independent validation. The project total excludes duplicate-group members, dismissed findings, wrong finds, and insufficient-reference findings. Only selected excerpts are published. Customer identity, project address, source identifiers, and private drawings are omitted. Corrections, permit outcomes, and financial savings have not been independently verified. A qualified professional should assess each finding against the complete project documents.