Warehouse and Distribution Building, Houston Metro, TX: 298 Issues Flagged
Check accessibility dimensions, overcurrent protection, and exhaust fan selections in a warehouse with office space.
Anonymized review · Published 2026-11-09
Free check on up to 10 drawing pages. Enterprise and volume pricing
- 1High · Architectural / PlumbingAccessible water closet centerline is dimensioned at 15 inches
- 2High · Mechanical / ElectricalCondensing unit breakers exceed the scheduled MOCP
- 3Medium · Mechanical / ElectricalWarehouse exhaust fans appear selected at too high a static pressure
Fig. 1 · Top findings, pinned on the set
- Potential findings
- 298
- Disciplines
- 7
- Published examples
- 3
- Critical or high examples shown
- 2
Checkers used on this project
Run the same check on your set →About this review
InspectMind ran an AI plan review on this industrial set and returned 298 potential findings across Architectural, Plumbing, Mechanical, Electrical, Structural, Civil, Fire Protection. The selected examples below show the document conflict, why it matters, and a suggested next step.
- Project type
- Industrial
- Disciplines
- Architectural, Plumbing, Mechanical, Electrical, Structural, Civil, Fire Protection
- Potential findings
- 298
- Published examples
- 3
- Published
- 2026-11-09
- Evidence status
- Selected from open findings in the source review record
What this review documents
Check accessibility dimensions, overcurrent protection, and exhaust fan selections in a warehouse with office space.
The documented result is a set of review findings. This case study does not establish that corrections were completed or that savings were realized. The examples below were marked useful in the source review record; they have been paraphrased to remove identifying details.
Key findings
- 1High
Accessible water closet centerline is dimensioned at 15 inches
Architectural / Plumbing · TAS 604.2
Restroom elevations dimension the accessible water closet centerline at 15 inches minimum from the side wall, while TAS 604.2 requires 16 to 18 inches.
Next step: Revise the dimension to 16 to 18 inches and update the restroom plans.
- 2High
Condensing unit breakers exceed the scheduled MOCP
Mechanical / Electrical
The condensing unit schedule lists 15A maximum overcurrent protection for twelve units, while the panel schedules show 20A breakers for the same units.
Next step: Resize the breakers to the scheduled MOCP or confirm revised equipment data.
- 3Medium
Warehouse exhaust fans appear selected at too high a static pressure
Mechanical / Electrical
Twenty unducted roof exhaust fans are each scheduled at 1.0 inch of static pressure, while the only resistance is an intake louver scheduled at 0.2 inch plus the curb and damper.
Next step: Confirm the system pressure and reselect the fans if a lower static pressure applies.
Issue categories
- Cat. 01Architectural / Plumbing
- Architectural / Plumbing findings in the selected review excerpts.
- Cat. 02Mechanical / Electrical
- Mechanical / Electrical findings in the selected review excerpts.
Review details and suggested questions
01Accessible water closet centerline is dimensioned at 15 inchesArchitectural / Plumbing · TAS 604.2
High
Architectural / Plumbing · TAS 604.2
Summary: Restroom elevations dimension the accessible water closet centerline at 15 inches minimum from the side wall, while TAS 604.2 requires 16 to 18 inches.
Why it matters: Fixtures set to the drawing fail accessibility inspection and require moving the rough-in.
Suggested next step: Revise the dimension to 16 to 18 inches and update the restroom plans.
RFI draft: Revise the dimension to 16 to 18 inches and update the restroom plans.
02Condensing unit breakers exceed the scheduled MOCPMechanical / Electrical
High
Mechanical / Electrical
Summary: The condensing unit schedule lists 15A maximum overcurrent protection for twelve units, while the panel schedules show 20A breakers for the same units.
Why it matters: Oversized breakers violate the equipment listing and are flagged at inspection.
Suggested next step: Resize the breakers to the scheduled MOCP or confirm revised equipment data.
RFI draft: Resize the breakers to the scheduled MOCP or confirm revised equipment data.
03Warehouse exhaust fans appear selected at too high a static pressureMechanical / Electrical
Medium
Mechanical / Electrical
Summary: Twenty unducted roof exhaust fans are each scheduled at 1.0 inch of static pressure, while the only resistance is an intake louver scheduled at 0.2 inch plus the curb and damper.
Why it matters: Overstated pressure can mean larger motors, heavier fans, and bigger feeders than the system needs.
Suggested next step: Confirm the system pressure and reselect the fans if a lower static pressure applies.
RFI draft: Confirm the system pressure and reselect the fans if a lower static pressure applies.
Anonymized, paraphrased excerpts from a completed project review. These three examples were selected editorially from findings the source review record kept open (not dismissed or marked wrong); that selection is not independent validation. The project total excludes duplicate-group members, dismissed findings, wrong finds, and insufficient-reference findings. Only selected excerpts are published. Customer identity, project address, source identifiers, and private drawings are omitted. Corrections, permit outcomes, and financial savings have not been independently verified. A qualified professional should assess each finding against the complete project documents.
Related case studies
Similar AI plan review results by project type and discipline.
- IndustrialLight Industrial Upfit, Charleston, SC: 105 Issues Flagged105issues · Architectural, Structural
- CommercialCommercial Kitchen & Multi-Discipline Plan Review: 284 Issues Found284issues · Architectural, Civil
- EducationCareer and Technical Center, West Virginia: 273 Issues Flagged273issues · Electrical, Fire Protection
- MEP CommercialEvents Center 30% Set: 258 Issues Including Critical Fire & Egress Violations258issues · Structural, Architectural
- CommercialRetail Building, Fort Worth Metro, TX: 254 Issues Flagged254issues · Fire Protection, Architectural
- MEP CommercialSelf-Storage Facility: 247 Issues Found in Pre-Permit Review247issues · Structural, Electrical