Warehouse and Distribution Building, Houston Metro, TX: 298 Issues Flagged

Check accessibility dimensions, overcurrent protection, and exhaust fan selections in a warehouse with office space.

Anonymized review · Published 2026-11-09

Free check on up to 10 drawing pages. Enterprise and volume pricing

298Potential findings
Flagged
  1. 1High · Architectural / PlumbingAccessible water closet centerline is dimensioned at 15 inches
  2. 2High · Mechanical / ElectricalCondensing unit breakers exceed the scheduled MOCP
  3. 3Medium · Mechanical / ElectricalWarehouse exhaust fans appear selected at too high a static pressure

Fig. 1 · Top findings, pinned on the set

Potential findings
298
Disciplines
7
Published examples
3
Critical or high examples shown
2

Checkers used on this project

Run the same check on your set →
Sheet 01·Case file

About this review

InspectMind ran an AI plan review on this industrial set and returned 298 potential findings across Architectural, Plumbing, Mechanical, Electrical, Structural, Civil, Fire Protection. The selected examples below show the document conflict, why it matters, and a suggested next step.

Project type
Industrial
Disciplines
Architectural, Plumbing, Mechanical, Electrical, Structural, Civil, Fire Protection
Potential findings
298
Published examples
3
Published
2026-11-09
Evidence status
Selected from open findings in the source review record

What this review documents

Check accessibility dimensions, overcurrent protection, and exhaust fan selections in a warehouse with office space.

The documented result is a set of review findings. This case study does not establish that corrections were completed or that savings were realized. The examples below were marked useful in the source review record; they have been paraphrased to remove identifying details.

Key findings

  1. 1

    Accessible water closet centerline is dimensioned at 15 inches

    Architectural / Plumbing · TAS 604.2

    High

    Restroom elevations dimension the accessible water closet centerline at 15 inches minimum from the side wall, while TAS 604.2 requires 16 to 18 inches.

    Next step: Revise the dimension to 16 to 18 inches and update the restroom plans.

  2. 2

    Condensing unit breakers exceed the scheduled MOCP

    Mechanical / Electrical

    High

    The condensing unit schedule lists 15A maximum overcurrent protection for twelve units, while the panel schedules show 20A breakers for the same units.

    Next step: Resize the breakers to the scheduled MOCP or confirm revised equipment data.

  3. 3

    Warehouse exhaust fans appear selected at too high a static pressure

    Mechanical / Electrical

    Medium

    Twenty unducted roof exhaust fans are each scheduled at 1.0 inch of static pressure, while the only resistance is an intake louver scheduled at 0.2 inch plus the curb and damper.

    Next step: Confirm the system pressure and reselect the fans if a lower static pressure applies.

Issue categories

Cat. 01Architectural / Plumbing
Architectural / Plumbing findings in the selected review excerpts.
Cat. 02Mechanical / Electrical
Mechanical / Electrical findings in the selected review excerpts.

Review details and suggested questions

01
Accessible water closet centerline is dimensioned at 15 inches

Architectural / Plumbing · TAS 604.2

High

Summary: Restroom elevations dimension the accessible water closet centerline at 15 inches minimum from the side wall, while TAS 604.2 requires 16 to 18 inches.

Why it matters: Fixtures set to the drawing fail accessibility inspection and require moving the rough-in.

Suggested next step: Revise the dimension to 16 to 18 inches and update the restroom plans.

RFI draft: Revise the dimension to 16 to 18 inches and update the restroom plans.

02
Condensing unit breakers exceed the scheduled MOCP

Mechanical / Electrical

High

Summary: The condensing unit schedule lists 15A maximum overcurrent protection for twelve units, while the panel schedules show 20A breakers for the same units.

Why it matters: Oversized breakers violate the equipment listing and are flagged at inspection.

Suggested next step: Resize the breakers to the scheduled MOCP or confirm revised equipment data.

RFI draft: Resize the breakers to the scheduled MOCP or confirm revised equipment data.

03
Warehouse exhaust fans appear selected at too high a static pressure

Mechanical / Electrical

Medium

Summary: Twenty unducted roof exhaust fans are each scheduled at 1.0 inch of static pressure, while the only resistance is an intake louver scheduled at 0.2 inch plus the curb and damper.

Why it matters: Overstated pressure can mean larger motors, heavier fans, and bigger feeders than the system needs.

Suggested next step: Confirm the system pressure and reselect the fans if a lower static pressure applies.

RFI draft: Confirm the system pressure and reselect the fans if a lower static pressure applies.

Anonymized, paraphrased excerpts from a completed project review. These three examples were selected editorially from findings the source review record kept open (not dismissed or marked wrong); that selection is not independent validation. The project total excludes duplicate-group members, dismissed findings, wrong finds, and insufficient-reference findings. Only selected excerpts are published. Customer identity, project address, source identifiers, and private drawings are omitted. Corrections, permit outcomes, and financial savings have not been independently verified. A qualified professional should assess each finding against the complete project documents.