Condensate failures appear after occupancy as ceiling floods—undersized pipe, missing secondary drain, or undocumented slope are drawing set errors to catch before construction, not installation mistakes discovered in the first hot season.
About 11 min read
Run mechanical checkerUpload drawings, specs, and codes. Eligible work emails get a $100 credit and cited issues in hours.
5+ issues or full refund · No demo required
Condensate is documented on mechanical drawings—sizes, slopes, routing, connections, secondary drains. When details are missing or wrong, installation reflects the drawing error. Plan examiners look under IMC 307 and UPC 814.3; drawings must show how the system drains, where overflow goes, and safe discharge. This sits within broader plumbing plan review when receptors cross disciplines.
Usually at peak cooling load in the first hot season—a rooftop AHU at 2–4 gallons per hour can overwhelm undersized lines. Without a working secondary path, water backs into ceilings and damages finishes below.
Minimum drain size must match scheduled cooling capacity—tables commonly require 3/4 inch minimum up to 20 tons, so 1/2 inch on a multi-ton unit is undersized. Review compares tonnage, outlet notes, and routed diameter before peak load causes overflow.
Secondary protection is required when primary failure could damage ceilings or equipment below—a common mistake is a primary drain shown while the auxiliary pan outlet is unconnected, undefined, or omitted.
IMC 307.2.1 requires at least 1/8 inch per foot toward discharge—the drawing should state slope, not only show a line between unit and receptor. Geometry that cannot achieve slope can fail after occupancy even when diameter looks acceptable.
Condensate must discharge to an approved place—not undefined sanitary ties or unapproved receptors. Confirm receptor and discharge with MEP coordination between mechanical and plumbing before construction.
Drawings should identify equipment served, primary size, routing, slope intent, and discharge—without capacity and approved disposal path, reviewers cannot confirm safe operation.
Document auxiliary pan outlet, secondary route, termination, or shutoff when primary failure could damage building components below.
Capacity, diameter, slope notes, secondary protection, overflow path, approved discharge, and ceiling or plumbing coordination—for plan check, missing items trigger comments even when intent seems clear to the design team.
The mechanical drawing checker compares equipment schedule, capacity, drain size, routing, slope, and secondary connections—with plumbing review for receptor and ceiling coordination.
Example: M2.01 shows a 5-ton AHU with 1/2-inch condensate while tables require 3/4-inch minimum; or primary drain routed but secondary pan outlet has no connected overflow path—equipment mark, sheets, and consequence included.
Undersizing, poor slope, clogging, wrong receptor, or missing working secondary overflow.
Often 3/4 inch up to 20 tons, 1 inch for 21–40 tons, 1-1/4 inch for 41–90 tons per UPC/IMC tables—size from equipment capacity.
When primary failure could damage components below—must be clearly shown and connected.
IMC 307.2.1: at least 1/8 inch per foot toward discharge, documented on the drawing.
Cross-references capacity vs drain diameter, slope at each run, and secondary pan routing—including undefined overflow locations flagged with sheet and equipment references.
Upload PDF drawings and specs. Get flagged issues with evidence and code citations in hours.
5+ issues or full refund · No demo required
Sample report: 282 issues found|Pricing after first check
227,181+ customer-visible issues across 2,000+ customer accounts